Lake Victoria North Water Services Board has received a Shs1.7 billion funding from the Belgium Government for the implementation of Vihiga Water Supply Project in Vihiga County.

Elgeyo Marakwet County Governor Hon Alex Tanui Tolgos hosted our CEO Eng Alfred Amombo and his team in his office to discuss matters pertaining to Chebara institutions and Water in the county.

The Board members include Hon. Joseph .K. Lagat (Chairman), Hezron Ripko (Member), Robert Watangwa(Member), Jacinta Odhiambo(Member), Abdi Sheikh Mohamed(Member), Peter KiteloChongeiywo(Member), Robert Namunyi Wawire(Member), Isaac Kipyego Maiyo(Member)

Board donates water tanks in Uasin Gishu and Kakamega Counties Lake Victoria North Water Services Board has donated 10,000lts water tanks each to Shitoto Girls Secondary School and St. Lukes Shenderema Secondary School in Mumias East Constituency

Latest News/ Updates

  • LVNWSB Chairman Joseph Lagat when he paid courtesy call to the Nandi County Commissioner
    LVNWSB Chairman Joseph Lagat when he paid courtesy call to the Nandi County Commissioner

    LVNWSB Chairman Joseph Lagat when he paid courtesy call to the Nandi County Commissioner

  • A water supply system for the Sengwers; The Kapcherop Water Supply Project
    A water supply system for the Sengwers; The Kapcherop Water Supply Project

    The indigenous people of Kapcherop Division


     

  • LVNWSB Chairman handing over Kabirirsang Water Project to the Nandi County government
    LVNWSB Chairman handing over Kabirirsang Water Project to the Nandi County government

    LVNWSB Chairman handing over Kabirirsang Water Project to the Nandi County government

  • Board shines in rural water supply
    Board shines in rural water supply

    It was another first for Lake Victoria North Water Services Board after being ranked the most improved Water Services Board in Kenya

  • Marathon
    Marathon

    The Cabinet Secretary, Ministry of Water and Irrigation Hon. Eugene Wamalwa joined the Lake Victoria North Water Services Board led by the Chairman Hon. Joseph Lagat and CEO

Community/Rural Projects

No.

PROJECT

SOURCE OF FUNDS

SCOPE OF WORKS

COST (KES)

LOCATION

IMPLEMENTORS

STATUS AND NUMBER OF BENEFICIARIES

  1.  

Emma Ilesi water and sanitation project

WSTF

Piped water supply rehabilitation and extension, Spring protections, VIP latrines

6,840,564

Ilesi location

Kakamega District

Ilesi CBO

Completed and commissioned serving 6,500 people

  1.  

Eshirombe water and sanitation project

WSTF

Drilling of boreholes, protection of springs, construction of had dug wells, VIP latrines

9,385,000

Eshirombe location

Butere District

 

Eshirombe CBO

Complete and commissioned, Targeted population of 12,000 people

  1.  

Acacia water and sanitation project

WSTF

New water supply project – pumping scheme with rising main and distribution network, VIP latrines

17,178,749

Sinoko Location, Lugari District.

 

Acacia CBO

Ongoing, but stalled due to lack of CDF part contribution, Target population of 8,790 people

  1.  

West Bunyala Water and sanitation project

WSTF

Rehabilitation of existing pipe network, protection of springs, VIP latrines

8,714,473

Bunyala West Location.

Kakamega District(Central

West Bunyala CBO

Complete and commissioned, targeted population of 4,680 people

  1.  

Namarambi Water and Sanitation project

WSTF

Construction of hand dug wells, protection of springs,

9,295,391

Namarambi location

Bungoma East

Target population 7000

Misemwa Youth Group

Complete and commissioned, targeted population of 7000 people

  1.  

Kipsigak  Water and sanitation project

WSTF

Piped water schemes -pumping and gravity systems, Hand dug wells, spring protections, VIP latrines

10,011,319

Kipsigak location

Nandi North District.

 

Kipsigak  Water and sanitation project CBO

Complete and commissioned, target population of 5,143 people

  1.  

Mwanzo Water and sanitation project

WSTF

Pumping piped scheme, Hand dug wells, spring protections, VIP latrines

7,999,449

South Marama location.

Butere District

Mwanzo CBO

Complete and commissioned, target population of 6,000 people

  1.  

West Kisa Water and sanitation project

WSTF

Drilling and equipping of boreholes, pipeline extensions, spring protections, VIP latrines

9,394,357

Butere  District, West  Kisa Location

West Kisa Water and sanitation project

Complete and commissioned, target population of 3250 people

  1.  

Buchenya Water and sanitation project

WSTF

Pumping piped scheme, VIP latrines

9,448,515

 

Marama location

Butere District

 

Buchenya CBO

Ongoing, targeting

9,705 people

10.   

Emungweso Water and sanitation project

WSTF

2No pumping piped schemes, spring protections, VIP latrines

9,379,927

Mulwanda location

Butere District

 

Emungweso Water and sanitation project CBO

Ongoing, targeting

5800 people

11.   

Eshibinga Water and Sanitation project

WSTF

20 hand-dug wells.

9 spring protection.

4 no Ferro cement tanks 30m3, VIP latrines

8,107,400

Kisa South location

Butere

Eshibinga CBO

Complete and commissioned, target population of 5,104 people

12.   

South West Bunyore Water and sanitation project.

WSTF

Pumping water supply scheme project, VIP latrines

8, 802,395

South-west Bunyore location

Emuhaya District.

Targeted population 6500 people.

South West Bunyore Water and sanitation project CBO

Complete and commissioned

Targeted population 6500 people

13.   

St Michael – Kosich Water and sanitation project

WSTF

Gravity piped water supply project, VIP latrines

11,335,186

Embobut Marakwet

Targeting  3262 people

St Michael – Kosich Water and sanitation project CBO

Ongoing, targeting

3262  people

14.   

Kaben traditional dancers  Water and Sanitation project

WSTF

Gravity piped water supply project, VIP latrines

11,470,595

Kaben

Marakwet

Targeting  4350 people

Kaben traditional dancers  Water and Sanitation project CBO

Ongoing, targeting

4350  people

15.   

Lufaco Water and sanitation project

WSTF

Hand dug well construction, spring protections, roof catchment systems, VIP latrines

8,600,549

Kabuyefwe  Bungoma North

Lufaco water Users Association

Complete and commissioned

Targeted population 15000 people

16.   

Soteni Water and Sanitation Project

WSTF

Hand dug well construction, spring protections, roof catchment systems, VIP latrines

7,277,850

Mbakalo Bungoma North

 

Soteni Village of Hope CBO

Complete and commissioned

Targeted population 12500 people

17.   

Turkwoyo Water and sanitation Project

WSTF

Gravity piped water supply project, VIP latrines

11,942,951

Koibirir Marakwet East. Targeting 4588 people

Turkwoyo Water and sanitation Project CBO

Ongoing, targeting

4588  people

18.   

Lufualula Water and Sanitation project

WSTF

Hand dug well construction, spring protections, roof catchment systems, VIP latrines

9,047,863

Naitiri Bungoma North.

 

Lufualula Water Users Association

Complete and commissioned

Targeted population 12100 people

19.   

Chepyakwai Water and sanitation project

WSTF

Gravity piped water supply project, VIP latrines

9,002,017

Ngeria Uasin Gishu

Chepyakwai Water Users Association

Ongoing, targeting

8500   people

20.   

Chepsaita Water and sanitation project

WSTF

Gravity piped water supply project, VIP latrines

9,115,179

Ngenyilel Uasin Gishu targeting 5,033 people

Chepsaita WUA

Complete and commissioned,

targeting 5,033 people

21.   

Nasira Water and sanitation project

WSTF

Pumping water supply scheme project, VIP latrines

8,886,912

Busibwabo Busia

Nasira WUA

Complete and commissioned,

targeting 4,815 people

22.   

Seiyot Water and Sanitation project

WSTF

Pumping water supply scheme project, VIP latrines

7,771,049

Kipsomba Uasin Gishu

Seiyot Water and Sanitation project WUA

Complete and commissioned,

targeting 9,876 people

23.   

World Hope Lemoru water project

WSTF

Pumping water supply scheme project, VIP latrines

7,927,529

Koisagat Uasin Gishu.

 

World Hope Lemoru WUA

Complete and commissioned,

targeting 6,800 people

24.   

Wekhakila Chetambe Water and sanitation project

WSTF

Pumping water supply scheme project, Hand dug wells, spring protections,VIP latrines

9,021,440

Chetambe Bungoma East.

Wekhakila Chetambe WUA

Complete and commissioned,

targeting 8,455 people

25.   

Kiminini Kona Water and sanitation project

WSTF

Pumping water supply scheme project, VIP latrines

11,989,150

Kiminini Bungoma North targeting

Kiminini Kona WUA

Complete and commissioned,

targeting 9,679 people

26.   

Soysambu Greeners Water and sanitation project

WSTF

Pumping water supply scheme project, VIP latrines

13,006,015

Tongaren Bungoma  North targeting 4,500 people

Soysambu Greeners WUA

Complete and commissioned,

targeting 4500 people

27.   

Masaba water and sanitation project

WSTF

Gravity piped water supply project, VIP latrines

7,625,713

Kaibei  Transnzoia

Masaba water WUA

Complete and commissioned, targeting15,200 people

28.   

Kakoli- Okuleu water and sanitation project

WSTF

Piped scheme water supply project – extension pipeline, VIP latrines

6,623,258

Okuleu  Teso targeting 6,340 people

Kakoli- Okuleu WUA

Ongoing, targeting

6340 people

29.   

Savannah water and sanitation project

WSTF

Pumping water supply scheme project, VIP latrines

7,888,769

Chetambe, Bungoma Targeting 8578 people

Nasasi WUA

Complete and commissioned, targeting 8575 people

30.   

Kokare Water and Sanitation project

WSTF

Piped scheme water supply project – extension pipeline, VIP latrines

8,176,124

Kokare, Teso, Targeting 4053 people

Kokare WUA

Complete and commissioned, targeting 4053 people

31.   

Kiboroa Water and Sanitation project

WSTF

Gravity piped water supply project, VIP latrines

7,718,100

Kiboroa,Trans-nzoia

Kiboroa WUA

Complete and commissioned, targeting 4053 people

32.   

Khalumuli water and sanitation project

WSTF

Roof catchment systems, hand dug wells, spring protections, VIP latrines

7,393,240

Sitikho, Bungoma

 

 

Complete and commissioned, targeting 6203 people

33.   

Seum water and sanitation project

WSTF

Gravity piped water supply project, VIP latrines

9,824,850

Kiptoror, Trans Nzoia

Targeting 13,231 people

Seum WUA

Complete and commissioned, targeting 13231 people

34.   

Osieko Nambo WatSan Project

WSTF

Pumping water supply scheme project, VIP latrines

8,265,000

South Bunyala, Busia

targeting 16,700

people

Osieko- Nambo WUA

Complete and commissioned, targeting 16700 people

35.   

Nangwe Bumenya WatSan Project

WSTF

Borehole drilling, spring protections, VIP latrines

7,792,400

Odiado, Busia targeting 12,795

people

Nangwe Bumenya CBO

Operational serving 12,795 people

36.   

Lukusi WatSan project

WSTF

Roof catchment systems, hand dug wells, spring protections, VIP latrines

7,766,460

Lukusi, Bungoma East

 

Chemavusi WUA

Operational serving 12,795 people

37.   

Indoli Nasewa WatSan project

WSTF

17 No. shallow wells

21No.spring protection

21 No. VIP latrines.

 

6,415,132

Nasewa, Busia targeting 11,052

people

Indoli WUA

Operational serving 10,052 people

38.   

Kaplolo

WSTF

Pumping system – piped water supply with 5Km distribution network

 

VIP latrines

9,270,965

Kaplolo, Uasin Gishu District

Kaplolo CBO

Ongoing

39.   

Mungoma water and sanitation project

WSTF

Pumping system – piped water supply with 7Km distribution network

 

VIP latrines

7,672,210

 

Mungoma, Vihiga District

Mungoma CBO

Ongoing

40.   

Jepkoyai water and sanitation project

WSTF

Pumping system – piped water supply with 5Km distribution network

 

VIP latrines

8,355,355

Jepkoyai, Vihiga District

Jepkoyai CBO

Ongoing